Project Timeline

Year Activity
2002 Preparation of planning application and Environmental Impact Statement
10th December, 2004 Submission of planning application to Fingal County Council
12th April, 2006 Fingal County Council grants planning permission subject to 39 conditions.
April, 2006 Dublin Airport lodges first part appeal to An Bord Pleanála.   Fourteen third party appeals are also submitted to An Bord Pleanála.
26th September, 2006 Oral Hearing
November, 2006 An Board Pleanála advises Dublin Airport that a decision on the proposed new runway is expected by 28th February 2007.
August 2007 Planning Permission Granted
July 2008 DAA announces intention to seek change in runway Planning conditions (click here for more)
2012 Opening of New Runway