December 15, 2016 Back to all news

 

Work is now starting on the first construction package for North Runway.  A number of pre-commencement conditions relating to the project, which received planning permission in August 2007, have now been discharged, allowing for the works to begin. This initial phase of the project will run for about eight months and will support up to 100 construction jobs. As previously indicated, the works will involve the diversion of the Naul Road, a realignment of the Forrest Little Road, and associated works including site fencing, services diversions, and site clearance and demolitions.

 
Click here for further information