July 15, 2020
Back to all news
Temporary traffic management measures are required to facilitate the laying of ducting for essential services at four locations adjacent Dublin Airport, as shown on the map above.
The works will take place at each location between 9.30am and 4.30pm on the following dates:
-
St Margaret’s Bypass Duct Crossing
Monday and Tuesday, 27 & 28 July 2020 -
Toberburr Road Duct Crossing
Wednesday and Thursday, 29 & 30 July 2020 -
Forest Road Duct Crossing
Monday and Tuesday, 3 & 4 August 2020 -
Castlemoate Road Duct Crossing
Wednesday and Thursday, 5 & 6 August 2020
We apologise for any inconvenience these measures may cause and we are happy to clarify any of the details outlined above. If you have any queries, please feel free to contact us directly on Freephone 1800 804 422 or via email on northrunway@daa.ie.