In order to facilitate remediation work to parts of the R108 adjacent North Runway, it is necessary to implement temporary traffic management measures on short stretches of the road, as indicated on the map below. The works will be completed in the following indicative tranches, with dates/durations dependent on weather conditions. We will, as always, do everything we can to undertake the works in the safest and most efficient manner in order to minimise any potential disruption to road users.
A – Wednesday, 13 October – One day
B – Thursday - Monday, 14 - 18 October (no weekend works) - Three days
C – Tuesday, 19 October – One day
D – Wednesday - Friday, 20 – 22 October - Three days
E – Monday, 25 October – One day